SCM01 is the first Smart City building in Phase One currently under construction.
It will consist of 12,000m2 of ready-to-use Grade A offices to be completed and handed over to the first business partners by 2010, as scheduled. 

TGS Co Ltd.  has been responsible of the construction of  the foundation and retaining structure works at SCM01 which have now been  completed and  has over 30 of its personnel  now engaged in the construction of the super-structure.

It also has a team of 15  workers at a precast concrete factory , preparing all the prefabricated structures that form part of SCM 001.